SECTION 2 - PROCEDURES
2-18 – JLG Lift – 3120240
22. Align the cylinder rod-end attachment holes with the
boom fly section attachment holes; install the pin
and secure the pin by installing washers and bolts.
23. Align the cylinder base-end attachment holes with
the boom mid section attachment holes; install the
trunnion pins and secure the pins by installing bars,
washers and bolts.
24. Slide the mid section into the base section. Allow the
retraction chains to trail between the bottom sur-
faces of boom sections; ensure that no twists exist in
chains. Shim the top of the mid section for a total of
1/16 inch (.062) clearance.
25. Install wear pads into the forward portion of the base
section. Shim boom, if necessary, for a total of 2/10
inch (.20) clearance.
26. Assemble the extension chain attachment and
adjustment assembly (mounted at aft of boom base
section) as follows:
a. Align the attaching holes of the chain attach-
ment clevis bolt with those of the extension
chain end; install the clevis pin through the
attaching holes. Install the washer and cotter pin
which secures the clevis pin through the chain
attachment assembly.
NOTE: Step 27 applies to 2 Section Boom Only.
27. Align the cylinder base-end attachment point with
those of the boom base section. If necessary, use an
auxiliary hydraulic power source to extend and
retract the cylinder rod for alignment. Install the
cross pin through the base boom section and cylin-
der rod. Secure pin by installing setscrew.
28. Align the cylinder rod-end attachment point with
those of the boom base section. If necessary, use an
auxiliary hydraulic power source to extend and
retract the cylinder rod for alignment. Install the
cross pin through the base boom section and cylin-
der rod. Secure pin by installing setscrew.
29. Align the chain attachment assembly holes with the
threaded mounting holes at the aft end of the boom
by installing the bolts and washers.
30. Insert the threaded end of the chain attachment cle-
vis bolt through the large hole of the chain attach-
ment weldment. Loosely install the jam nut and nut
onto the threaded end of clevis bolt.
31. Assemble and install the retraction chain attachment
and adjustment assembly as follows:
a. Place clevis bolt on bottom plate and place top
plate onto clevis assembly. Secure clevis bolt
with clevis pins, washers and new cotter pins.
b. Insert chain attach blocks between clevis plates
ensuring attachment points are properly aligned.
Secure block in position with bolts, nuts and
new cotter pins.
c. Align retraction chains with clevis attach blocks;
secure chains with clevis pins, washers and new
cotter pins.
d. Position the bolt end of the extension-adjust-
ment clevis into the boom mounted bracket.
Secure the chain-adjusting assembly by install-
ing the jam nut and nut.
e. Position the chain adjustment shield over the
chain adjustment assembly; secure the shield
by installing the bolts and washers.
32. Adjust retract and extend chains to the proper
torque. (See step a. adjusting procedures of para-
graph 2-6).
33. Install the hydraulic hoses, electrical cables, and the
harnessing power track components as follows:
a. Properly position the fly section carrier tube with
carrier tube bracket installed at the side of the
boom. Align the attachment holes the forward
end of the carrier tube with those of the fly sec-
tion mounting plate. Secure the carrier tube by
installing the bolts, washers, lock washers and
nuts. Align the support bracket with attachment
holes in the mid boom and secure with bolts and
washers.
b. Properly position the assembled hoses, electri-
cal cable, and the harnessing powertrack onto
the base section carrier tube. Carefully feed the
proper hose and cable ends through the fly sec-
tion carrier tube and into the hole in the boom fly
section. Properly align the powertrack end with
the attachment point of the fly section carrier
tube; install the bolts, washers, lock washers
and nuts which secure the powertrack to the car-
rier tube.
c. Carefully feed the remaining hose and cable
ends aft through the base section carrier tube.
Properly align the remaining powertrack end
with the attachment point of the base section
carrier tube; install the bolts, washers, lockwash-
ers and nuts which secure the powertrack to car-
rier tube.
d. Ensure all hoses and cables are properly routed
through the carrier tube and powertrack. Tighten
or install all clamping or securing apparatus to
the hoses or cables, as necessary.